PROVIDENCE ST. VINCENT M-LEVEL REBUILD
![](/media/filer_public/1f/ab/1fab09e8-31cd-4936-847d-98f4ed8a45b7/cj1fddetr0005audwsrtpdlxj-2012-10-25-10-04-06-am-removing-louversfull.jpg)
PROCESS
Temporary air was supplied by bringing in additional air from a new handler on the roof while the other units were shut down.
![](/media/filer_public/65/2e/652e7dcc-67af-4cb4-bb44-4e1a43e91b72/cj1fen9aq000vgedwhce7kwnv-photo-sep-20-1-52-35-pmfull.jpg)
TEMPORARY DUCT INSTALLATION
Temp duct installed from roof down side of building to support removal of units on mechanical level.
![](/media/filer_public/dc/60/dc60f531-26ea-4105-944f-964b767c9d0d/cj2y50iup000js6dwlpa83v25-temp-ductfull.jpg)
MOCKUPS
Temporary enclosures were set up and tested off site to isolate and remove the old concrete in order to install the new concrete.
![](/media/filer_public/02/d2/02d2b8ea-733e-470b-8411-34b3d5adc3fe/cj1ff681j0013gedwfgozsczu-2012-05-17-002full.jpg)
NEW FLOOR
The temporary enclosures installed on the job site allowed for a contained area to install new waterproof membranes.
![](/media/filer_public/8e/a5/8ea5f963-b9a3-4fdd-81ed-9d9bb46089f8/cj1ffg2fu0017gedwun872h46-2012-11-30-6-57-53-zone-19full.jpg)
EQUIPMENT INSTALL
Equipment move in day.
![](/media/filer_public/34/d0/34d0b8cc-638b-43cd-85d7-2235cc4c2da6/cj2xf16kt00123idwpsv9aq7j-crane-pick-1140full.jpg)
CHALLENGE
Work areas on the level were close quarters with multiple disciplines working in the same area.
![](/media/filer_public/45/5b/455b12f7-bd94-45d2-926e-fb2612a60ad2/cj1fdvxaf000daudwufi2sizq-2012-10-27-08-48-20-amfull.jpg)
Mark Reusser, Anderson Construction Senior Superintendent
3D SCANNING
Laser scanning BIM models allowed the placement of temporary ductwork to be repurposed later in the project.
![](/media/filer_public/ca/71/ca717a19-24b7-4203-94e5-2d8886a24652/cj1cu38270012e5dwzsnqolek-image2full.jpg)
Rick Arnett, djcoregon.com