PROVIDENCE ST. VINCENT M-LEVEL REBUILD

The project was to replace the existing concrete floor on the mechanical level. This mechanical floor is in the middle of a 10 story fully operational hospital. This involved removal of 37 Air Handlers and replacing them with newer centralized units. While keeping the hospital supplied with air to stay up and running.

PROCESS

Temporary air was supplied by bringing in additional air from a new handler on the roof while the other units were shut down.

TEMPORARY DUCT INSTALLATION

Temp duct installed from roof down side of building to support removal of units on mechanical level.

MOCKUPS

Temporary enclosures were set up and tested off site to isolate and remove the old concrete in order to install the new concrete.

NEW FLOOR

The temporary enclosures installed on the job site allowed for a contained area to install new waterproof membranes.

EQUIPMENT INSTALL

Equipment move in day.

CHALLENGE

Work areas on the level were close quarters with multiple disciplines working in the same area.

3D SCANNING

Laser scanning BIM models allowed the placement of temporary ductwork to be repurposed later in the project.